Temporary Works Registers: One Live Record from Brief to Removal
TWInst Editorial Team · 3 min
The temporary works register is the project’s central index of temporary works. It shows what exists, where it is located, who controls it and whether it is awaiting design, checking, installation, verification, release or removal.
The register should be created early and updated throughout the project.
Recommended information
Each register entry may include:
- Unique temporary works identification number
- System description and exact location
- Responsible coordinator and delivery team
- Designer and checker
- Risk or design-check classification
- Design brief and required inputs
- Drawing, calculation and revision references
- Planned installation, loading and removal dates
- Design, check, inspection and permit status
- Changes, non-conformances and open actions
- Dismantling and final closeout status
Status descriptions should be simple, consistent and linked to objective evidence.

Maintaining control
The register should be reviewed during coordination meetings and reconciled with field activities. A dashboard may help communication but should not replace the controlled drawings, certificates, inspection records and permits behind each status.
Closed items should remain traceable so the project can demonstrate how they were controlled and capture lessons for future work.

If a temporary work is not visible in the register, it is difficult to prove that its risks and approvals are controlled.
General educational information only. Project-specific work should follow applicable requirements, approved engineering documents, manufacturer instructions and the project's temporary works procedure.