Understanding the Temporary Works Process

Temporary works are structures or systems used to enable, support or protect construction activities and permanent works. Although they may remain for only a limited period, they can carry significant loads and should be managed through a controlled process from initial planning to final dismantling.

01

Plan

Identify and plan all temporary works items expected on the project, including their purpose, location, interfaces, required dates, duration and removal sequence.

Before work begins, establish:

  • A project Temporary Works Procedure
  • Defined roles, responsibilities and approval authorities
  • A Temporary Works Register or Matrix listing the required items
  • Risk classifications and design-checking categories
  • An Inspection and Test Plan
  • Required hold points, permits and records
  • A preliminary schedule for design, installation, use and removal

The register should be updated when new temporary works are identified or when project conditions change.

Three people reviewing drawings and physical scale models of formwork and shoring at a table, with a construction site visible beyond
Temporary works planning session, the required items, their sequence and who is responsible are agreed before work begins.
02

Design

Prepare a clear design brief covering the intended use, loads, dimensions, ground conditions, interfaces, construction stages and environmental conditions.

The solution should be designed and independently checked to the level required by the project procedure. Installation, loading, alteration and dismantling stages should all be considered, not only the completed arrangement.

Temporary works planning in action
Early planning connects the required temporary works, design information and construction sequence.
03

Install

Temporary works should be installed by competent personnel using the approved drawings, method statement and manufacturer’s instructions.

Foundations, bracing, connections, access, edge protection and temporary stability should be maintained throughout installation. Unauthorized substitutions or modifications should not be accepted.

A crew assembling modular slab falsework on adjustable props and bracing a vertical wall form panel on a concrete deck
Crew installing modular falsework and wall forms, the built arrangement should follow the approved design.
04

Inspect and Authorize

Inspect the completed installation against the approved design before loading or use.

A Permit to Load or Use should release the applicable hold point before every defined loading or use cycle required by the project procedure. A new assessment or permit may also be required following relocation, alteration, damage or changing site conditions.

Periodic inspections should continue while the temporary works remain in service. Additional inspections should follow severe weather, impact, settlement, ground movement or any event that could affect stability.

Record deficiencies and confirm that the necessary corrective actions are completed.

Inspecting wall formwork and slab shoring
Installation should be checked against the approved design before the applicable hold point is released.
05

Use and Monitor

Temporary works should remain within their approved loading, access, operational and environmental limits.

During use:

  • Prevent unauthorized changes
  • Complete the required periodic inspections
  • Monitor settlement, movement and deterioration
  • Maintain foundations, bracing and connections
  • Control loading and nearby activities
  • Record and close identified deficiencies
An inspector checking an adjustable steel shoring prop that supports loaded concrete formwork, with a second worker on a scaffold walkway
Inspector monitoring loaded concrete falsework, checks continue while the system is in service.
06

Unload and Dismantle

Before removal, confirm that the temporary works are no longer required and that the permanent works, or another supporting system, can safely carry the applicable loads.

Where required by the procedure, issue a Permit to Unload/Dismantle before removal begins. This may also be called a Permit to Strike or Permit to Dismantle.

Removal should follow the approved sequence while maintaining stability at every stage. Do not remove supports, reshoring, bracing or excavation support without confirmation that the required conditions have been achieved.

Staged formwork removal at a concrete site
Dismantling should follow an approved sequence after the required release has been issued.
Key principle
Plan→Design→Install→Inspect→Authorize→Use and Monitor→Unload and Dismantle

No stage should proceed until its required checks, records and hold points have been completed.